INDUSCO ISOLATIONS INC.

Decontamination

Asbestos Decontamination

Leaders in Decontamination and Asbestos Removal

When a building is said to be contaminated, it is generally a case of asbestos contamination. This highly carcinogenic material used to be popular in the industrial sector and in the composition of construction material due to its resistance to fire and its insulating trait. 


We’re the leaders in asbestos decontamination and removal. Rigorous protective measures are imposed on work sites until all residual pollution is eliminated before the buildings are demolished or restored.

Asbestos Decontamination

Leaders in Decontamination and Asbestos Removal

When a building is said to be contaminated, it is generally a case of asbestos contamination. This highly carcinogenic material used to be popular in the industrial sector and in the composition of construction material due to its resistance to fire and its insulating trait. 

We’re the leaders in asbestos decontamination and removal. Rigorous protective measures are imposed on work sites until all residual pollution is eliminated before the buildings are demolished or restored.

Asbestos Removal Principles and Objectives

Buildings Intended for Destruction

The prior removal of materials containing asbestos must be carried out whenever technically possible.

Buildings in Use

If a diagnosis reveals the presence of materials containing friable asbestos (flocking, insulation and false ceilings) which constitutes a risk for the occupants of the building, the owner must work on it regularly. 

The Steps for Efficient Asbestos Removal

Asbestos decontamination work must comply with the regulations in force, which aim to ensure the safety of those involved and of the environment. It requires specific equipment and protection systems.


Before starting the decontamination operations, a dusting is performed and the premises are moved. All equipment (networks, removable partitions, fluids, doors, etc.) that is not in direct contact with asbestos and that is not contaminated by fibres is removed.


The area to be treated is then confined. This containment prevents any leakage of asbestos fibres from the site. For this purpose, the walls are protected, and the work area is sealed by static or dynamic techniques.

  • Static Containment

    The access to the building is hermetically sealed, the walls and floors are cleaned, then all the non-washable or impossible to decontaminate structures in the area to be decontaminated are isolated by materials such as a double plastic film, varnishes and paints.


    The tightness of the containment is then tested by introducing smoke, which must not be able to escape. A permanent renewal of air is necessary during this work. Air inlets and evacuations are arranged in the tight envelope.


    Airlocks (airtight rooms between two different environments) allow the passage of personnel, equipment and the evacuation of polluted waste.

  • Dynamic Containment

    Dynamic containment refers to the renewal of the air in the decontaminated area, depressurizing it in comparison to the outside. In the case of a leakage in the tight envelope, the air movement would be from the outside to the inside of the building so that the asbestos fibres cannot be released into the environment.


    Air extractors, equipped with high-performance absolute filters, trap the asbestos fibres and ensure this vacuum.


    The system must renew the air volume six times an hour.


    The following steps involve the handling of contaminated materials or materials containing friable asbestos. As a result, the amount of particulate matter in the confined environment increases significantly during decontamination operations.


    All personnel are provided with personal protective equipment:


    • Assisted Ventilation Breathing System (mask)
    • Disposable Overalls
    • Disposable Gloves and Boots

Dry Removal


Dry dismantling (or curing) consists of removing materials that have been in direct contact with or contaminated by asbestos fibres (false ceiling tiles, networks, etc.) to gain access to materials containing friable asbestos. Materials made accessible can be removed. The preferred removal techniques have the following advantages:

Limiting the exposure of workers to asbestos dust
Causing the least amount of fibre emissions into the atmosphere
Facilitating the evacuation of the removed debris

Wet Removal


This technique is the most effective in reducing dust emissions. The asbestos material is completely saturated with water before being removed. Once the asbestos is removed, the surfaces are brushed and then vacuumed. Multiple inspections are performed before the site is dismantled:

Visual checks of the state of the structures done by the company and the project manager and subsequently by an independent contractor
Measurement of residual airborne dust
Final inspection done by the project manager to ensure that there is no more asbestos

If the inspection is satisfactory, the first layer of containment is removed. Restitution measurements are performed 48 hours later, to allow ambient dust to settle. When the dust level is less than 5 fibres/liter of air, the air extraction and the containment barriers are removed, and a final cleaning is performed.


After dismantling and before the re-occupation of the premises, the owners must perform a final inspection of the treated surfaces by an independent construction technician. The visual inspection is completed by a measurement of the dust level. If it is less than 5 f/l (rate satisfying the fire safety regulations), the premises can be re-equipped, then reoccupied. If the work did not allow the removal of all the asbestos-containing flocking, insulation and false ceilings (case of confinement), a periodic control of the state of conservation of the materials will have to be carried out every 3 years (minimum) or at the time of any substantial modification brought to the building or of its use.

Contaminated Waste Management


Before and during the extraction of asbestos, polluting waste is evacuated from the building sites. The elimination process must be done according to the environmental codes, and is divided into three categories:

Category 1
Asbestos Materials
Personal Protective Equipment
Filters
Polyane Films
Category 2
Material or object that has been in contact with asbestos (construction rubble, insulation, etc.) that cannot be decontaminated
Category 3
Smooth materials that are polluted but can be decontaminated by washing (metal structures, heating pins, etc.)

Category 1 and 2 waste is placed in waterproof bags inside the site and transported to the "waste" airlock. The bags are cleaned once, placed in a second bag which is washed before leaving the confined area, and placed in large bags to facilitate their handling.


This last waste, labelled as hazardous, is sent to the treatment centres for inerting or burying, depending on its nature. An asbestos waste tracking slip ensures their traceability. The treatment centre returns the last part to the project manager, accompanied by a waste acceptance certificate. After the treatment, it delivers a certificate confirming that the waste has been treated. Category 3 waste, known as "cleanable" waste, is washed in the "waste lock" and then treated in a conventional landfill.


It is important not only to take the presence of asbestos in a building seriously, but also to leave the decontamination to asbestos removal experts who will be able to solve the problem by rigorously following the protection rules, for the health and safety of all.

Contact Us
Share by: